Three Gorges Cofferdam Blasting Test

Dynatronic blasting test

Project name: Three Gorges Cofferdam Blasting Test

Brief introduction:  After the major project of the Three Gorges Dam was completed in 2006, the upstream cofferdam was required to be demolition. The cofferdam will burst into the water after the cofferdam is blown, it will have a certain impact on the dam. Therefore, it is necessary to monitor the impact force of the water hammer wave and test the vibration and displacement data generated on the dam body before and after the explosion.

Previous
Previous

Monitoring for pigging process of oil West-East gas pipelines

Next
Next

Shanghai Expo Axis Online Monitoring